Infomaniak and Gruyère Energie have put their joint planning application for a 2.5MW data center in Bulle on public display, the two companies [said](https://news.infomaniak.com/en/data-center-bull...

Infomaniak and Gruyère Energie Seek Permits for 2.5MW Bulle Data Center

Abdul-Rahman Oladimeji

Abdul-Rahman Oladimeji

November 19, 2026

Infomaniak and Gruyère Energie have put their joint planning application for a 2.5MW data center in Bulle on public display, the two companies said. The application went on public display on 13 November 2026. Subject to permits, construction iscoolingpost.comFeatured: Industrial heat exchange and cooling infrastructure connected to Infomaniak's Swiss data center network. due to start in the first half of 2027 and the facility is due online in 2028.

Under the joint announcement, Infomaniak builds and operates the data center, while Gruyère Energie provides the land, builds the heat recovery and reuse installations and supplies the site with renewable electricity. The companies say those roles remain subject to contracts still to be finalised. Infomaniak intends to finance the build from its own resources, phasing the investment in line with commissioning and ramp-up.

The building is planned for 170 server racks on a footprint of about 1,200 square meters, in an industrial zone in Bulle in the canton of Fribourg. Its 2.5MW of IT capacity is twice that of Infomaniak's D4 data center in Geneva. Storage servers will be air-cooled. Compute and AI servers will use closed-loop direct liquid cooling, and the design has no cooling tower, no evaporation and no water withdrawal once the circuits are filled.

Heat from both cooling loops is intended to reach Gruyère Energie's district heating network through the utility's heat pumps. At full load, the servers' 2.5MW of electricity is expected to produce about 2.5MW of heat continuously. Gruyère Energie estimates the site will supply around 28GWh of heat a year after the heat pumps, avoiding about 2.8 million litres of heating oil and up to 7,500 tonnes of CO2 annually. The utility expects heat output across its network to reach 180GWh by 2030.

Infomaniak has traded on the SIX Swiss Exchange since 1 October 2026, employs 337 people and reported service billings up 26.5% in the first half of 2026. The company operates three data centers in Switzerland, Data Center Dynamics reported. Netzwoche reported that Bulle is the largest infrastructure project in the Infomaniak group. Gruyère Energie employs 400 people and runs a 180km district heating network supplied by more than 95% renewable energy.

Baxtel tracks 55 data center facilities in Switzerland, operated by 19 providers. STACK INFRASTRUCTURE and Digital Realty Trust lead the market with four sites each, and the Zurich metro accounts for 33 of the facilities, four of them under construction, according to Baxtel's Switzerland market page.


Related on Baxtel


Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.