Data Center News

Read SpaceXAI Discloses $6.1M Stormwater Permit Exposure at Mississippi AI Campus
SpaceXAI, Elon Musk's artificial intelligence company, disclosed Thursday that Mississippi environmental regulators say construction started at three of its Southaven sites before required stormwat...

SpaceXAI Discloses $6.1M Stormwater Permit Exposure at Mississippi AI Campus

October 24, 2026 xAI: MACROHARDRR

SpaceXAI, Elon Musk's artificial intelligence company, disclosed Thursday that Mississippi environmental regulators say construction started at three of its Southaven sites before required stormwater permits were in place, with potential penalties of up to $6.1 million. The admission came in a...

Read more
Read Google Expands Voltus Capacity Deal To More Than 1GW In PJM
Google will buy 1,070 MW of additional flexible capacity from Voltus in the PJM grid region. The companies [announced](https://www.voltus.co/press/google-voltus-1gw) the expansion of their Bring Yo...

Google Expands Voltus Capacity Deal To More Than 1GW In PJM

October 23, 2026 United States

Google will buy 1,070 MW of additional flexible capacity from Voltus in the PJM grid region. The companies announced the expansion of their Bring Your Own Capacity agreement on Oct. 22, adding 1,070 MW to the 100 MW they committed in June. Voltus aggregates flexible capacity from homes and...

Read more
Read TerraWatt Proposes Up to 1GW Data Center at Former Alton Steel Site
TerraWatt has proposed buying Alton Steel's 381-acre Illinois mill site and building a data center campus of up to 1GW there. The developer announced the plan on [Oct. 21](https://static1.squarespa...

TerraWatt Proposes Up to 1GW Data Center at Former Alton Steel Site

October 23, 2026 Illinois

TerraWatt has proposed buying Alton Steel's 381-acre Illinois mill site and building a data center campus of up to 1GW there. The developer announced the plan on Oct. 21 for the Riverbend Technology Center at 5 Cut Street in Alton. Alton Steel would sell the land, TerraWatt would develop and own...

Read more
Read Microsoft Files for 422MW Three-Building Data Center Campus in Rome, Georgia
Microsoft filed for state review on October 20 of a three-building data center campus in Rome, Georgia, with 422MW of planned capacity. The [Development of Regional Impact application](https://dca....

Microsoft Files for 422MW Three-Building Data Center Campus in Rome, Georgia

October 22, 2026 Hyperscale Data Center

Microsoft filed for state review on October 20 of a three-building data center campus in Rome, Georgia, with 422MW of planned capacity. The Development of Regional Impact application covers 349 acres at 0 Huffaker Road and 1,659,000 square feet of floor space. Microsoft owns the land, bought in...

Read more
Read Cleveland Extends Data Center Moratorium Through January 29, 2027
Cleveland City Council voted on the night of Oct. 19 to extend the city's moratorium on new data centers through Jan. 29, 2027, or until council enacts permanent rules. The extension keeps zoning p...

Cleveland Extends Data Center Moratorium Through January 29, 2027

October 21, 2026 Cleveland

Cleveland City Council voted on the night of Oct. 19 to extend the city's moratorium on new data centers through Jan. 29, 2027, or until council enacts permanent rules. The extension keeps zoning permits and occupancy certificates frozen for new standalone data centers and also covers expansions...

Read more
Read Amazon Drops 800,000 Sq Ft Data Center Campus In Loudoun County Deal
Amazon Data Services has withdrawn its application to build four data centers on the former George Washington University campus in Ashburn, Virginia, ending a months-long standoff with Loudoun Coun...

Amazon Drops 800,000 Sq Ft Data Center Campus In Loudoun County Deal

October 21, 2026 Ashburn: Data Center Alley

Amazon Data Services has withdrawn its application to build four data centers on the former George Washington University campus in Ashburn, Virginia, ending a months-long standoff with Loudoun County. Officials announced the agreement, called Project Potomac Promise, at the Oct. 20 Board of...

Read more
Read Memphis Council Rejects Proposed 18-Month Data Center Moratorium
Memphis councilors rejected an 18-month data center moratorium, opting instead for a 135-day pause on new applications and a 90-day review of digital infrastructure projects. The longer proposa![be...

Memphis Council Rejects Proposed 18-Month Data Center Moratorium

October 21, 2026 Memphis

Memphis councilors rejected an 18-month data center moratorium, opting instead for a 135-day pause on new applications and a 90-day review of digital infrastructure projects. The longer proposal followed public opposition and protests at an October 6 council meeting. After a five-and-a-half-hour...

Read more
Read AEP And X-energy Study 960MW SMR Plant To Power Amazon In Indiana
X-energy and American Electric Power will study a 960 MW advanced nuclear plant at a retired coal station in Sullivan County, Indiana, with Amazon funding development work and positioned to buy the...

AEP And X-energy Study 960MW SMR Plant To Power Amazon In Indiana

October 20, 2026 Indiana

X-energy and American Electric Power will study a 960 MW advanced nuclear plant at a retired coal station in Sullivan County, Indiana, with Amazon funding development work and positioned to buy the plant's output. The companies announced a joint development agreement on Oct. 19 covering...

Read more
Read Entergy Adds 440MW Solar PPA For Google West Memphis Expansion
Entergy Arkansas plans roughly $600 million of new generation and transmission for [Google](https://baxtel.com/data-centers/google)'s data center campus in [West Memphis](https://baxtel.com/data-ce...

Entergy Adds 440MW Solar PPA For Google West Memphis Expansion

October 20, 2026 Arkansas

Entergy Arkansas plans roughly $600 million of new generation and transmission for Google's data center campus in West Memphis, Arkansas, with Google covering the cost. The utility announced a second phase of its service agreement on Oct. 19 that adds a 440 MW solar contract and two battery...

Read more
Read Anthropic, Nscale in Talks for Second $45B Deal at West Virginia Campus
[Nscale](https://baxtel.com/data-centers/nscale) is in talks to sell Anthropic roughly $45 billion of AI computing capacity from a second building at its Monarch data center campus in West Virginia...

Anthropic, Nscale in Talks for Second $45B Deal at West Virginia Campus

October 20, 2026 Nscale: Monarch Compute Bldg2

Nscale is in talks to sell Anthropic roughly $45 billion of AI computing capacity from a second building at its Monarch data center campus in West Virginia, a deal that would nearly double the AI lab's commitments to the Nvidia-backed neocloud. Bloomberg first reported the talks on Monday, and...

Read more
Read Microsoft To Fund 1,100MW Of Indiana Generation Under 20-Year NiSource Deal
Microsoft will pay for all the generation and transmission needed to serve its La Porte, Indiana data center campus under a 20-year electric service agreement with [NiSource](https://www.nisource.c...

Microsoft To Fund 1,100MW Of Indiana Generation Under 20-Year NiSource Deal

October 19, 2026 Northwest Indiana

Microsoft will pay for all the generation and transmission needed to serve its La Porte, Indiana data center campus under a 20-year electric service agreement with NiSource announced Oct. 16. Service starts in 2028. The utility's unregulated affiliate, NiSource Generation Company, will add...

Read more
Read NiSource And Microsoft Sign 20-Year Deal For 1,100MW Of Indiana Power
Microsoft will fund about 1,100 MW of new generation and transmission in northern Indiana and buy the output for 20 years under an agreement with [NiSource](https://www.nisource.com/news/article/ni...

NiSource And Microsoft Sign 20-Year Deal For 1,100MW Of Indiana Power

October 19, 2026 Hyperscale Data Center

Microsoft will fund about 1,100 MW of new generation and transmission in northern Indiana and buy the output for 20 years under an agreement with NiSource, the holding company that owns Northern Indiana Public Service Company. Announced Friday, the deal covers the La Porte data center campus...

Read more
Read Alcoa To Sell Idle Massena East Smelter Site For Up To $315M Data Center Build
Alcoa will sell portions of its long-idled Massena East aluminum smelter in northern New York to a developer that plans to build a data center on the property, a transaction the company values at u...

Alcoa To Sell Idle Massena East Smelter Site For Up To $315M Data Center Build

October 19, 2026 New York State

Alcoa will sell portions of its long-idled Massena East aluminum smelter in northern New York to a developer that plans to build a data center on the property, a transaction the company values at up to $315 million. Alcoa disclosed the definitive agreement in its third-quarter 2026 results on...

Read more
Read Alcoa Sells New York Smelter to Data Center Developer in $315m Deal
Alcoa Corporation has agreed to sell parts of its former Massena East smelter in upstate New York to an unnamed data center developer for up to $315 million. The buyer was not disclosed, though cry...

Alcoa Sells New York Smelter to Data Center Developer in $315m Deal

October 19, 2026 New York

Alcoa Corporation has agreed to sell parts of its former Massena East smelter in upstate New York to an unnamed data center developer for up to $315 million. The buyer was not disclosed, though cryptominer NYDIG has previously been linked to the site, where an affiliate has filed plans for a data...

Read more
Read Top Data Center News for 12th-17th October, 2026
**[Microsoft Acquires 600 Acres for Data Center Development in Woodward, Iowa](https://baxtel.com/news/microsoft-acquires-600-acres-for-data-center-development-in-woodward-iowa)**
**Microsoft has ...

Top Data Center News for 12th-17th October, 2026

October 19, 2026 United States

Microsoft Acquires 600 Acres for Data Center Development in Woodward, Iowa Microsoft has acquired 600 acres in Woodward, around 30 miles northwest of Des Moines, Iowa, valued at around $37.4 million, for a potential gigawatt scale data center campus expected to support cloud computing and data...

Read more
Read Digital Realty Picks Kokomo for 1GW Campus, Its First in Indiana
[Digital Realty](https://baxtel.com/data-centers/digital-realty-trust) wants to build its first [Indiana](https://baxtel.com/regions/indiana) data centers in Kokomo, proposing a three-building camp...

Digital Realty Picks Kokomo for 1GW Campus, Its First in Indiana

October 17, 2026 Indiana

Digital Realty wants to build its first Indiana data centers in Kokomo, proposing a three-building campus with roughly 1GW of IT capacity on 476 acres of greenfield land. The global REIT published a project page for the development after city officials confirmed its interest earlier this month,...

Read more
Read Meta Named on 400MW Kentucky Campus With 40-Year Local Tax Break
Mason County Fiscal Court voted unanimously on Oct. 13 to approve a development and community revenue agreement with Meta, ending two years in which the company behind a planned hyperscale campus n...

Meta Named on 400MW Kentucky Campus With 40-Year Local Tax Break

October 16, 2026 Kentucky

Mason County Fiscal Court voted unanimously on Oct. 13 to approve a development and community revenue agreement with Meta, ending two years in which the company behind a planned hyperscale campus near Maysville, Kentucky was kept unnamed (Mason County Fiscal Court announcement). The site covers...

Read more
Read Mason County Approves 40-Year Tax Deal for Meta's 400MW Kentucky Campus
The Mason County Fiscal Court voted unanimously on Oct. 13 to approve three agreements that clear the way for [Meta](https://baxtel.com/data-centers/meta) to build a hyperscale data center campus o...

Mason County Approves 40-Year Tax Deal for Meta's 400MW Kentucky Campus

October 16, 2026 Kentucky

The Mason County Fiscal Court voted unanimously on Oct. 13 to approve three agreements that clear the way for Meta to build a hyperscale data center campus on nearly 3,000 acres near Maysville in northeastern Kentucky. The approvals, set out in the county's news release, cover a 40-year...

Read more
Read LightEdge Considers Data Center Project Near Des Moines, Iowa
LightEdge plans to develop a colocation data center on ten acres in Boone Business Park, Iowa, about 48 miles northwest of Des Moines.
The Boone County Economic Growth Corporation has signed a let...

LightEdge Considers Data Center Project Near Des Moines, Iowa

October 16, 2026 Iowa

LightEdge plans to develop a colocation data center on ten acres in Boone Business Park, Iowa, about 48 miles northwest of Des Moines. The Boone County Economic Growth Corporation has signed a letter of intent for the land sale. The city’s planning commission has approved the site plan for...

Read more
Read BlackRock CEO Warns US Data Center Construction Slowdown Could Trigger Recession
BlackRock CEO Larry Fink warned that a nationwide US data center construction moratorium could trigger a recession, given the economy’s growing reliance on AI infrastructure investment. JLL estimat...

BlackRock CEO Warns US Data Center Construction Slowdown Could Trigger Recession

October 16, 2026 United States

BlackRock CEO Larry Fink warned that a nationwide US data center construction moratorium could trigger a recession, given the economy’s growing reliance on AI infrastructure investment. JLL estimates data center development will require $3 trillion in investment by 2030. Global occupancy stands...

Read more