Overview
Tuscany is a small data centre market in central Italy. Most capacity sits in Arezzo, where Aruba opened its first data centre in 2002. Its second followed in 2012, and Aruba billed it as Italy's first Tier IV data centre. Florence has smaller network and edge sites, including a Rai Way edge data centre that opened in December 2024.
The Market Today
Aruba's Arezzo buildings serve its hosting and cloud customers, and the newer one holds an ANSI/TIA-942 Rating 4 certificate. In July 2026 Comtel signed a memorandum with H2-Era Green Valley to build a data centre in Figline e Incisa Valdarno, at the former Bekaert steel-cord plant southeast of Florence. A solar plant on a former lignite mine nearby is to power it, with surplus power for hydrogen.
Advantages
-
Geothermal power. Enel Green Power's geothermal plants around Larderello and Monte Amiata cover about a third of Tuscany's electricity demand.
-
Solar sites. The Region has authorised a 79.2 MW solar plant to supply the Figline project.
Challenges
-
Small market. Tuscany has no cloud region and no large colocation campus, and Aruba runs most of its capacity.
-
Early pipeline. The Figline data centre has no planning permission yet, and Comtel has not published its capacity, user or opening date.
Power and Policy
Terna runs the transmission grid, and e-distribuzione distributes power at the region's data centre sites. The Region authorises renewable plants such as Figline's solar park, and data centres follow the national single authorisation created in 2026.