| Scale42: Kitee (Puhos) |
Kitee, a city in eastern Finland, is finalizing contract negotiations with an unnamed European op...
|
||
| YIT: Kontiolahti |
The planned data center by Finnish construction company YIT in Kontiolahti is in the early develo...
|
||
| Scale42: Liperi |
Scale42 is planning a 60MW AI data center in Liperi’s Välikangas industrial area, with constructi...
|
North Karelia lies on the Russian border in eastern Finland, with Joensuu as its regional center. The region has no colocation market yet. Developers have reserved industrial land for large data centers in Kitee, Liperi and Kontiolahti, and all three projects are still before construction.
Scale42 leads the pipeline with two projects. In Kitee, it plans a data center in the Puhos industrial area, and the city granted the project a planning exception to speed the build. In Liperi, the council approved a land lease and a preliminary sale in the Välikangas industrial area in May 2026. YIT holds a planning reservation in Kontiolahti's Vellamo business area at Lehmo. Its plan sends server heat into the Kontiolahti and Joensuu district heating networks.
Fingrid runs the national grid. Its 2026 to 2035 development plan, published in December 2025, includes reinforcements for eastern Finland and North Karelia. Large sites need their own 110 kV substations, and the Puhos project plans one on site.