Microsoft: Hillcrest Campus (AVC01)

Short Code: AVC01
Year Built: 2024

Sites on this Campus:

░░░░░░░ Login to view SqFt
Total Building Size
░░░░ Request Dataset MW
Total Power

The original test fit design for the Hillcrest project included eight data center buildings totaling 336MW of total capacity – including five 48MW buildings, one 28.8MW, and one 19.2MW building – but would have resulted in 'impacts to nearly every wetland and stream feature' located on the site. The plan was reduced to three planned buildings with reduced total power capacity

Map and Nearby Locations

This Facility
Microsoft Azure Sites
Nearby Facilities

Point MaxInterested in this information?Contact us Power Growth Over Time

+0% since 2022
Operational
Construction
Planned
Prospective
In Doubt
Withdrawn
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Sites within 15 miles of Edge CampusInterested in this information?Contact us

Distance Site About
0.08 miles StationInterested in this information?Contact us
This data center is a part of Amazon's Hillcrest Campus in South Hill, VA.
0.13 miles Campus ThreeInterested in this information?Contact us
2.94 miles Park BetaInterested in this information?Contact us
Microsoft is developing a two-building data center campus in South Hill, Virginia.
3.05 miles Hyperscale Data CenterInterested in this information?Contact us
3.07 miles Station OneInterested in this information?Contact us
3.08 miles Hyperscale Data CenterInterested in this information?Contact us
3.12 miles Hyperscale Data CenterInterested in this information?Contact us
3.18 miles Hyperscale Data CenterInterested in this information?Contact us
3.38 miles Hyperscale Data CenterInterested in this information?Contact us
14.00 miles CoreInterested in this information?Contact us
14.36 miles Prime HubInterested in this information?Contact us
14.40 miles Park PlusInterested in this information?Contact us
14.45 miles Global CenterInterested in this information?Contact us
14.77 miles Core PlazaInterested in this information?Contact us
14.84 miles Campus PlusInterested in this information?Contact us
14.90 miles Tower AlphaInterested in this information?Contact us
14.96 miles Tower OneInterested in this information?Contact us
15.42 miles MaxInterested in this information?Contact us
15.46 miles ParkInterested in this information?Contact us
15.48 miles Tower UltraInterested in this information?Contact us
15.52 miles MetroInterested in this information?Contact us
15.54 miles Station PlusInterested in this information?Contact us
15.55 miles Metro StationInterested in this information?Contact us
15.55 miles Cloud PointInterested in this information?Contact us
15.55 miles Campus BetaInterested in this information?Contact us
15.57 miles Cloud StationInterested in this information?Contact us
15.59 miles Center PrimeInterested in this information?Contact us
15.61 miles Park MaxInterested in this information?Contact us
Microsoft is building another data center campus near its Boydton site. Microsoft Corporation bought the vacant site where the Mecklenburg Correctional Center was once located at 960 Prison Road.
15.61 miles East CenterInterested in this information?Contact us
15.62 miles Core CenterInterested in this information?Contact us
15.62 miles Cloud PointInterested in this information?Contact us
15.65 miles Central TowerInterested in this information?Contact us
15.65 miles NorthInterested in this information?Contact us
15.69 miles Cloud PlazaInterested in this information?Contact us
15.76 miles Valley OneInterested in this information?Contact us
The Boydton site has strong fiber connectivity from existing routes supporting a government data center in the region.

East CenterInterested in this information?Contact us Data Center Photos See all

Site plan as of June 2022
Source: Baxtel
State of Azure Locations as of July 2019
Source: Microsoft
Conceptual Azure Regions and Availability Zones diagram
Source: Microsoft

Operating Company

Operated by:

Microsoft uses Containers (called ITPACs) to build out its data centers. These Containers are Shipping Containers fitted with all the necessary climate control, networking, server racks and other hardware necessary to be a “mini” data center all in one.

Azure Regions

An Azure region is a set of data centers deployed within a latency-defined perimeter and connected through a dedicated regional low-latency network.

With more global regions than any other cloud provider, Azure gives customers the flexibility to deploy applications where they need to. Azure is generally available in 46 regions around the world, with plans announced for 8 additional regions.

Geographies

An Azure geography is a discrete market, typically containing two or more regions, that preserves data residency and compliance boundaries.

Geographies allow customers with specific data-residency and compliance needs to keep their data and applications close. Geographies are fault-tolerant to withstand complete region failure through their connection to our dedicated high-capacity networking infrastructure.

Availability Zones

Availability Zones are physically separate locations within an Azure region. Each Availability Zone is made up of one or more data centers equipped with independent power, cooling, and networking.

Availability Zones allow customers to run mission-critical applications with high availability and low-latency replication.

426
Facilities
70
Markets

News See all

Read Microsoft Secures Capacity At Pure DC Data Center In Finland
Pure DC has launched the first phase of its Seinäjoki, Finland, data center project, with Microsoft reportedly among the customers leasing capacity at the site. The initial phase will deliver 110MW...

Microsoft Secures Capacity At Pure DC Data Center In Finland

July 14, 2026 Microsoft Azure

Pure DC has launched the first phase of its Seinäjoki, Finland, data center project, with Microsoft reportedly among the customers leasing capacity at the site. The initial phase will deliver 110MW of capacity with an estimated investment of $1.7 billion. Pure DC has been developing plans for the...

Read more
Read Microsoft Reports 25% Rise in CO₂ Emissions Amid Data Center Expansion
Microsoft reported a 25 percent year-on-year rise in carbon emissions, with total Scope 1, 2, and 3 emissions increasing to 20.29 million metric tons of CO₂e as data center expansion accelerated. T...

Microsoft Reports 25% Rise in CO₂ Emissions Amid Data Center Expansion

July 10, 2026 Microsoft Azure

Microsoft reported a 25 percent year-on-year rise in carbon emissions, with total Scope 1, 2, and 3 emissions increasing to 20.29 million metric tons of CO₂e as data center expansion accelerated. The company said the jump was largely due to its decision to stop using unbundled renewable energy...

Read more
Read National Grid Ventures Invests $1.75bn in Gas Plant for Microsoft Texas Data Center
National Grid Ventures (NGV), the commercial arm of National Grid, has acquired a 35% stake in Joulent for $1.75 billion to support development of power infrastructure for large data centers. The i...

National Grid Ventures Invests $1.75bn in Gas Plant for Microsoft Texas Data Center

July 04, 2026 Microsoft Azure

National Grid Ventures (NGV), the commercial arm of National Grid, has acquired a 35% stake in Joulent for $1.75 billion to support development of power infrastructure for large data centers. The investment will help fund Project Kilby, a 2.67GW natural gas facility being developed with Chevron....

Read more
Read Microsoft’s First Data Center at Mount Pleasant, Wisconsin Campus Now Operational
The first data center at Microsoft’s Mount Pleasant, Wisconsin campus is now officially operational, the company confirmed on June 23. Construction was completed just over two years after the proje...

Microsoft’s First Data Center at Mount Pleasant, Wisconsin Campus Now Operational

June 23, 2026 Microsoft Azure

The first data center at Microsoft’s Mount Pleasant, Wisconsin campus is now officially operational, the company confirmed on June 23. Construction was completed just over two years after the project was first announced. The site is part of Microsoft’s “Fairwater” data center design and will form...

Read more
Read Microsoft Begins Construction of La Porte Data Center Campus
Microsoft has broken ground on a new data center campus in La Porte, Indiana. Brad Smith, Microsoft vice chair and president, announced in a LinkedIn post that the groundbreaking ceremony took plac...

Microsoft Begins Construction of La Porte Data Center Campus

June 18, 2026 Microsoft Azure

Microsoft has broken ground on a new data center campus in La Porte, Indiana. Brad Smith, Microsoft vice chair and president, announced in a LinkedIn post that the groundbreaking ceremony took place on June 17. Smith wrote: "Today we broke ground in La Porte, Indiana, alongside Mayor Tom Dermody,...

Read more
Read More News

Podcasts See all

See More Podcasts

Documents See all

Ready to Level up Your
Data Center Strategy?