Overview
Gävleborg lies on the Baltic coast north of Stockholm and holds Microsoft's largest footprint in Sweden. Microsoft runs three campuses around Gävle and Sandviken. An operator hotel in Gävle and a small colocation site in Hudiksvall serve local networks and businesses. Since 2024, developers have planned new campuses in the county's north, close to 400 kV stations and cheaper power.
History
Microsoft bought land from the Gävle and Sandviken municipalities in late 2018. It also bought 200 hectares from private owners at Stackbo, near Valbo. In 2020 Netnod extended its Sundsvall internet exchange to Gävle. Microsoft opened its Sweden Central cloud region in November 2021, with data centres in Gävle, Sandviken and Staffanstorp. In June 2024 it pledged SEK 33.7 billion for cloud and AI capacity at the same three sites. In April 2025 it paused new building in Sandviken, saying it had built as much as the existing power lines allowed.
The Market Today
Microsoft runs campuses at Ersbo in Gävle, at Stackbo near Valbo and in Sandviken. Vattenfall Eldistribution is running regional lines to all three from the Stackbo transmission station of Svenska kraftnät (Svk). Microsoft is still building on every campus. The new Sandviken lines are due at the end of 2027.
Gävle Energi's city network, GavleNet, runs an operator hotel in central Gävle. Netnod's regional exchange for mid-Sweden connects networks there and in Sundsvall. Internetport runs a small colocation business in Hudiksvall, with one hall above ground and one below.
New projects sit in the north of the county. Hyperco, owned by DAMAC's Edgnex since April 2025, won a building permit in October 2026 for a campus at Lingbo in Ockelbo. The site lies next to Svk's Grönviken 400 kV station, and Hyperco targets first operations in November 2027. EcoDataCenter opened consultation in September 2026 on a campus at Norrsundet harbour, on the site of a former pulp mill. It plans to build in stages over about ten years.
Advantages
-
Transmission access. Svk's Stackbo and Grönviken stations bring the 400 kV grid close to the main sites.
-
Cheaper northern power. Lingbo and Norrsundet sit in bidding zone SE2. In 2025 the average SE2 spot price was less than half the SE3 price.
-
Municipal support. Gävle and Sandviken sold Microsoft its campus land. Ockelbo adopted a detailed plan for the Lingbo data-centre site in June 2026.
Challenges
-
Grid capacity. Svk maps less than 50 MW of free withdrawal capacity in Gävleborg for 2026. Applications for new electricity use in the county total 3,200 MW in its queue.
-
Line delays. Vattenfall's last concession for the new Sandviken lines became final in August 2025. Building them required Gävle to close its Rörberg airport, and that decision became final only in March 2026, after appeals to three courts.
-
Southern prices. Gävle and Sandviken sit in SE3, where prices run higher than in the north. Data centres also pay the full national electricity tax.
Trends
-
AI capacity. Microsoft's 2024 plan included more than 20,000 advanced GPUs for its Swedish sites.
-
Moving north. New campuses target Ockelbo and Norrsundet, in SE2 and near transmission lines. Norrsundet reuses former pulp-mill land.
-
Power sets the pace. Hyperco says power allocation and customer demand will set its build rate. Microsoft's Sandviken expansion follows the new lines.
Power and Policy
Svk runs the 400 kV and 220 kV transmission grid and the connection queue. Vattenfall Eldistribution runs the regional grid around Gävle and Sandviken, and Ellevio runs it across much of the county's north. Gävle Energi and Sandviken Energi distribute power in their towns. The Swedish Energy Markets Inspectorate (Energimarknadsinspektionen, Ei) regulates the grid companies.