FFO AI: Oder 6 is module 6 of 6 on SCALE ONE, the hyperscale and AI data center campus that Frankfurt DATA FFO AI, a company of the Berlin developer SolWo Group, plans off Müllroser Chaussee in the Markendorf industrial area of Frankfurt (Oder), Brandenburg. The campus lies southwest of the former First Solar works. The city adopted the development plan in November 2026, and the plan allows a data center of up to six modules.
A new 380/110 kV substation near Hohenwalde and a 4 km underground 110 kV cable will connect the campus to the transmission grid. The campus plan includes backup generators, a gas power plant area, gas storage and battery storage. Waste heat will feed the Stadtwerke Frankfurt (Oder) district heating network, and the developer will contribute €15 million to that network.
Site History
- November 2026: Frankfurt (Oder) city council adopted the development plan and signed the urban development contract with the developer.
- March 2026: The city council unanimously approved the draft development plan for the "Industrie- und Gewerbepark an der B87".
- October 2023: The city started the development plan procedure for the site.