CyrusOne acquired this 45-acre plot of land in Quincy in 2016, and started construction in early 2023.

The 45-acre campus can expand to a total of 930,000 square feet with 720,000 colocation square feet with up to 120,000 square feet for class A office space.

Map and Nearby Locations:

1025 D St NW
Click Map to begin Search

Sites within 15 miles of CyrusOne Quincy

Show SqM
Distance Site About
0.19 miles NTT Data Quincy
The data center was first built by Dell in 2012. Subsequently sold to NTT Data in the Perot services deal.
0.65 miles Microsoft Quincy MWH
Microsoft was one of the first companies to build a data center in Quincy. In 2006 Microsoft constructed the first phase (470,000 square feet) of the ‘Columbia Data Center’ in Quincy, Washington
1.99 miles Yahoo-Oath Quincy
"DC1" 180,000 sqft and 26 MW
"DC2" 151,000 sqft and 26 MW
2.42 miles H5 Quincy
H5's 63-acre data center campus was a former Intuit facility.
2.54 miles Sabey Intergate.Quincy
Intergate.Quincy is a 525,000 square foot data center five building campus in Central Washington. Like Intergate. Columbia, Intergate.Quincy offers the advantage of low power rates, close proximity to the region’s power grid, and a mild climate ideal for efficient, evaporative cooling.
2.63 miles Vantage Quincy Campus
Vantage operates a 68-acre campus with three large data centers.
2.65 miles Vantage WA11
2.68 miles Vantage WA13
2.72 miles Vantage WA12
15.63 miles MIcrosoft: Malaga, WA
Microsoft has filed plans to build a campus with three data centers in Malaga, Washington. Microsoft acquired more than 100 acres in a deal spread across two phases; Phase I is the Lojo Property, 72.5 acres at 5375 Malaga Alcoa Highway for which Microsoft paid $6.6 million.
15.79 miles Microsoft: Malaga 2
Microsoft has filed plans to build a campus with three data centers in Malaga, Washington. The development will construct the first building on the site by the end of 2025, with potential for two more buildings by 2027.
15.90 miles Microsoft: Malaga 3
Microsoft has filed plans to build a campus with three data centers in Malaga, Washington. The development will construct the first building on the site by the end of 2025, with potential for two more buildings by 2027.
18.69 miles T-Mobile East Wenatchee
T-Mobile's data center is on Sabey's campus.
18.76 miles Sabey Intergate.Columbia
The Intergate.Columbia campus in East Wenatchee sits on 30 acres of land. The campus is fully leased, but Sabey is expanding on the campus.
19.23 miles Salcido Pangborn Data Center
Salcido is a Cyrpto Mining hosting provider. Salcido calls it a "Tier 0" data center apparently in reference to the redundancy design
19.44 miles BitDeer: Washington

CyrusOne Quincy Data Center Photos


Rendering of the proposed CyrusOne Quincy Facility

Campus plan

Operating Company

CyrusOne Inc, incorporated on July 31, 2012, is an owner, operator and developer of enterprise-class, carrier-neutral, multi-tenant datacenter properties. CyrusOne's data centers are purpose-built facilities.

The CyrusOne National IX Platform (the National IX Platform) delivers interconnection across states and between metro-enabled sites within the CyrusOne footprint and beyond. The platform enables data transfer and accessibility for customers by uniting all of the Company’s data centers. CyrusOne’s portfolio is located in several domestic and international markets. It has domestic properties in Chicago, Dallas, Houston, Phoenix, San Antonio and Cincinnati.

Company History:


July 2010: Cincinnati Bell acquires CyrusOne [r3]
Jan 2013: CyrusOne IPO [r2]
July 2014: Acquired Cervalis [r1]

References:


r1. Businesswire link July 1, 2015
r2. NASDAQ.com link Jan 18, 2013
r3. CyrusOne PR link

70 Facilities Owned
27 Markets Served
933.42 Megawatts
View Company

News

Read More News

Files

Name Date Added Description
cyrusone_dcss_quincy_2016a February 2018

Quincy Data Sheet (PDF)

health_impact_assessment_for_cyrusone_data_center_in_quincy April 2019

Washington Dept of Ecology studies the impact of the CONE Quincy facility

2022-pnw1_pacific-northwest-quincy October 2022

data sheet (2022)