Creekstone Energy: Delta Gigasite, Utah

Site planned for 2027 and has expansions through 2035
Lot Size: 1,143 acres

Creekstone Energy is developing the Delta Gigasite, a hyperscale AI data center campus on 1,143 acres southeast of Delta in Millard County, Utah, near 4500 East and US-50. The site comprises 10 contiguous parcels rezoned from Agriculture-20 to Heavy Industrial by the Millard County Commission on June 3, 2025; the original applicant was Fibernet MercuryDelta LLC, whose infrastructure assets were subsequently acquired by Creekstone.

Groundbreaking occurred in December 2025, with Phase 1 baseload deliveries targeted for end of 2027 from on-site natural gas reciprocating engines, supplemented by Torus battery and flywheel storage. The campus operates fully behind the meter via a 345 kV private transmission line, with a gas interconnect agreement executed for 43,000 Dth/day supplied via the Kern River Pipeline.

Creekstone holds a long-term solar lease on 13,000 acres of Utah state trust land (SITLA) adjacent to the campus, the largest solar lease in Utah history; Millard County granted zoning approval for Phase 1 solar development with an 18-month build target. Non-binding MoUs are in place with Zeo Energy (solar plus long-duration storage, February 2026) and EnergySolutions (next-generation nuclear including SMR options, December 2025; commercial operation targeted 2030 to 2035).

The facility is carrier-neutral with 100G/400G-ready infrastructure and 20+ long-haul fiber routes intersecting at the site. BluSky AI Inc. is the only confirmed tenant, allocated 25 acres. Creekstone has committed $17 billion of investment to Utah over 20 years per the Governor's Office of Economic Opportunity.

The IPP plant sits roughly 15 miles northwest of the campus; the connection is via Creekstone's 345 kV private transmission line and the existing IPP transmission corridor, not literal land adjacency.

Map and Nearby Locations:

Near 4500 E & US-50
Creekstone Energy LLC Sites
Nearby Facilities

Sites within 15 miles of Creekstone Energy: Delta Gigasite, Utah

Distance Site About
4.17 miles Fibernet MercuryDelta Campus
Fibernet MercuryDelta, LLC has successfully requested the rezoning of 1,143.8 acres at approximately 4500 E & HWY 50 Delta, changing its designation from Agriculture 20 (Ag-20) to Heavy Industrial (HI).
4.52 miles BluSky AI: Delta, UT
BluSky AI has signed a letter of intent to acquire 25 acres of land in Utah for a new data center.
11.94 miles Joule HP Compute Campus
The 4,000-acre site, located in Millard County, is projected to have multi gigawatt capacity and launch in 2026.

Creekstone Energy: Delta Gigasite, Utah Data Center Photos (See all)

Operating Company

Operated by:

Creekstone Energy was founded to remove the fundamental limitations on AI growth by solving the energy and scalability challenges. We fuse a Silicon Valley startup vision with enterprise-grade execution, aiming to be the foundational layer for the AI era—where power is plentiful, latency is minimal, and compute can scale without compromise.

1
Facilities
0
Markets

News (See all)

Read More News

Podcasts (See all)

See More Podcasts

Documents (See all)

Ready to Level up Your
Data Center Strategy?