CGE: Konin

Planned
Future facility in planning stage
Operated by: CGE S.A.

CGE: Konin

Site planned for 2028 and has expansions through 2030
PUE: 1.21
Utility Provider: PSE
Lot Size: 16 acres

The project company CGE 171FF holds a building permit, issued by Konin in May 2026, for a complex of four main server buildings with offices, underground fuel tanks and heat recovery. Its grid connection conditions from PSE are at the Pątnów 220 kV substation. The first stage is up to 100 MW of IT load, with construction planned from the first quarter of 2027; the full 260 MW depends on later phases. Energa Obrót signed a letter of intent in 2026 to act as the project's energy partner.

Site History

  • September 2026: Energa Obrót, the city of Konin and CGE signed a letter of intent on power supply.
  • May 2026: Konin issued the building permit.
  • April 2026: CGE announced the project.
  • January 2026: Konin issued the environmental decision.
  • September 2025: PSE issued grid connection conditions.

Map and Nearby Locations

Brunatna
CGE S.A. Sites
Nearby Facilities

CGE: Konin Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Operating Company

Operated by: CGE S.A.

Centralna Grupa Energetyczna S.A. (CGE S.A.) is a Polish-owned company founded in 2012 and based in Posada, near Konin. It develops solar and battery storage projects across Greater Poland through project companies.

Its largest project is an AI and HPC data center campus in Konin of up to 260 MW of IT load, held by the sister company CGE 171FF, which CGE markets to joint-venture partners and tenants.

CGE S.A. History:

  • In May 2026, Konin issued the building permit for the Konin data center.
  • In April 2026, CGE announced the Konin data center project.
  • Founded in 2012 in Posada.
0
Facilities
0
Markets

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.