Year Planned: 2028

DC Tomelloso is a proposed AI data center campus in Tomelloso, Ciudad Real. It was added to the EdgeMode and Blackberry AIF joint venture in January 2026. After Blackberry AIF ended that joint venture in September 2026, its holding company Black Artificial Intelligence SL formed DC Estate Tomelloso SL for the project. No site, land deal or permit has been published.

Site History

  • September 2026: Black Artificial Intelligence SL forms DC Estate Tomelloso SL, and Blackberry AIF ends the EdgeMode joint venture.
  • January 2026: The project joins the EdgeMode and Blackberry AIF joint venture pipeline.

Map and Nearby Locations

Tomelloso
Blackberry AIF Sites
Nearby Facilities

Blackberry AIF: DC Tomelloso Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Operating Company

Operated by:

Blackberry AIF (BAIF) is a Spanish data center developer based in Seville and led by José Antonio Mora. It develops large AI campuses on leased rural land through one project company per site, under its IberData Hub platform, and plans on-site power from solar, batteries and natural-gas fuel cells. Its projects include sites in Mora (Toledo), Córdoba, Vianos (Albacete), Torrecampo (Córdoba), Cáceres and Tomelloso (Ciudad Real). In 2026 it formed a holding company, Black Artificial Intelligence SL, for its newer project companies.

Blackberry AIF History:

  • In September 2026, Blackberry AIF ended its joint venture with EdgeMode and took back the project companies.
  • In January 2026, Blackberry AIF and EdgeMode formed a joint venture over five Spanish campus projects.
  • In July 2025, Blackberry AIF and EdgeMode announced plans to combine.
  • In September 2024, Blackberry AIF announced its first green data center project, GDC Córdoba.
  • Founded in 2024 in Seville.
0
Facilities
0
Markets

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.