Exanorth AS, wholly owned by Bitzero, has mined bitcoin at Tunnsjødalsveien 178 in Namsskogan since 2021, on a 50,000 m² property beside the Tunnsjødal hydropower station, the largest power plant in central Norway. The site draws 40 MW through mining containers. Statnett has reserved 70 MW more, and the two 60 MVA transformers for a new substation reached Norway in November 2026. Skanska has a development agreement for two to four buildings of up to 110 MW in total, and Bitzero targets 320 MW in a later phase.
In May 2026 Bitzero and One Qode signed a binding letter for a 15-year lease of the full 110 MW.
Site History
- November 2026: The 60 MVA transformers arrived in Norway.
- May 2026: Bitzero and One Qode signed a binding letter for 110 MW.
- August 2024: NVE granted the concession for the new substation.
- June 2022: Statnett connected 40 MW.
- October 2021: Bitzero bought 66% of Exanorth, and it bought the rest in 2022.