1911 Walbrzych Data Centre

Latest Podcast ul. Mariana Jachimowicza (plot 92/1)
Planned
Future facility in planning stage
Operated by: 1911 Data Centres

1911 Walbrzych Data Centre

Site planned for 2027 and has expansions through 2028
Utility Provider: Tauron Dystrybucja

The project sits on ul. Mariana Jachimowicza in the Poniatów district of Wałbrzych, inside the WSSE Invest-Park special economic zone and opposite the Toyota plant. The developer reports 52 MW of contracted grid power from Tauron Dystrybucja, split between a medium-voltage feed and a 110 kV connection, and markets the site for liquid-cooled AI deployments with a modular path to further expansion. Wałbrzych issued the building permit in October 2025.

Site History

  • February 2026: Clearing of the plot began.
  • October 2025: Wałbrzych issued the building permit.
  • 2025: The project received a special economic zone support decision.

Map and Nearby Locations

ul. Mariana Jachimowicza (plot 92/1)
1911 Data Centres Sites
Nearby Facilities

1911 Walbrzych Data Centre Power Growth Over Time

Operational
Construction
Planned
Prospective
Land Bank
In Doubt
Currently Operational
across NN Request Dataset sites
Under Construction
NN Request Dataset sites currently building
Planned / Prospective
NN Request Dataset sites announced, but haven't started construction

Operating Company

Operated by: 1911 Data Centres
0
Facilities
0
Markets

Podcasts See all

Listen to E9 - Building Hyperscale AI Data Centers in Rural America With Wes Cummins
Listen to E8: Inside ERCOT, Black Start, Winter Storm Uri, and AI Data Center Load
Listen to E7:Now we are cooking with Gas! Behind the Meter Solutions with Nick Kruse
See More Podcasts
Get Quotes
Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.