Data Center Campus
Sify's Rabale data center campus in Navi Mumbai is designed for 12 towers, powered by dedicated 110 KV (towers 1-3) and 220 KV GIS (towers 4-6) substations. The campus features triple access paths with quad fiber connectivity and runs on 70% renewable energy (99 MW from solar/wind). It offers both BTS and multi-tenant options with dual meet-me-rooms and robust network connectivity through multiple providers. The facility primarily serves hyperscalers, OTT, BFSI, Manufacturing, Media, and Healthcare sectors.
Buildings
| Site | Operator | Status | Operational | Building Size | Built |
|---|---|---|---|---|---|
| Sify: Rabale DC1 | Sify Technologies |
Operational
|
░░░░ Request Dataset MW | — | 2014 |
| Sify: Rabale DC2 | Sify Technologies |
Operational
|
░░░ Request Dataset MW | — | 2014 |
| Sify: Rabale DC4 | Sify Technologies |
Operational
|
░░░ Request Dataset MW | — | 2021 |
| Sify: Rabale DC5 | Sify Technologies |
Operational
|
░░░░ Request Dataset MW | — | 2024 |
| Sify: Rabale DC11 | Sify Technologies |
Under Construction
|
— | — | 2026 |
| Sify: Rabale DC12 | Sify Technologies |
Under Construction
|
— | — | 2026 |
| Sify: Rabale DC6 | Sify Technologies |
Under Construction
|
— | — | 2026 |
| Sify: Rabale DC7 | Sify Technologies |
Under Construction
|
— | — | 2026 |
| Sify: Rabale DC10 | Sify Technologies |
Planned
|
— | — | 2028 |
| Sify: Rabale DC8 | Sify Technologies |
Planned
|
— | — | 2028 |
| Sify: Rabale DC9 | Sify Technologies |
Planned
|
— | — | 2028 |
| Sify: Rabale DC3 | Sify Technologies |
Operational
|
— | — | — |