Microsoft is planning 400,000 sqft Campus in Hoffman Estates

Microsoft is planning 400,000 sqft Campus in Hoffman Estates

Marketing  HQ

Marketing HQ

March 09, 2021

According to plans submitted to the Hoffman Estates council, Microsoft aims to build two data centers on the 53-acre site on the north side of Lakewood Blvd in two phases. Phase one would see a 250,000 sq ft (23,200 sqm) building erected by the end of 2022. The second phase would be a 150,000 sq ft (14,000) building. The plans include adding an electrical substation.

The expected cost is $200 million.
 