| Greensky: Halsua |
Greensky is developing a data center area of about 185 hectares along Lestijärventie in Halsua, n...
|
||
| Greensky: Toholampi (Kiertokangas) |
Greensky is developing a data center site of about 80 hectares at Kiertokangas in Toholampi, next...
|
||
| Fu-Gen: Toholampi (Marjokangas) |
Fu-Gen is developing a data center with battery storage on about 47 hectares at Marjokangas, nort...
|
||
| Tekova: Perho |
Tekova is developing a data center on plots of about 4 hectares in the Isokangas industrial area ...
|
Central Ostrobothnia lies inland from the Gulf of Bothnia in western Finland, with Kokkola as its regional center. It has no operating data centers. Developers come for the region's wind farms, including the 455 MW Lestijärvi wind farm, the largest built in Finland, and for Fingrid's new 400 kV lines.
Four projects sit in zoning or permitting. Greensky plans a large data center area along Lestijärventie in Halsua, near Fingrid's Laurinneva substation, and a second site at Kiertokangas in Toholampi. Fu-Gen plans a data center with battery storage at Marjokangas, also in Toholampi. Tekova is the furthest along: it applied for a building permit in Perho's Isokangas industrial area in October 2026.
Fingrid connects large loads at 400 kV, with new substations planned at Laurinneva and Ullava. Herrfors runs a 110 kV line past the Marjokangas site. The Toholampi and Halsua boards accepted zoning initiatives during 2026.
Tell us what you're looking for. We respond within one business day.