Overview
Genoa, the capital of Liguria, is a cable-landing and interconnection market in Italy rather than a large colocation hub. Four subsea cables land in the city and three more are planned. Equinix and Vodafone announced the GN1 hub in February 2021, and it opened in January 2022. The 2Africa cable made its first landing there in April 2022. Sparkle opened its Genoa Digital Hub in Lagaccio in 2023, when the BlueMed cable arrived and the Ge-DIX exchange signed on.
The Market Today
Equinix's GN1 has a direct fibre link to the company's ML5 data centre in Milan. Sparkle's Genoa Digital Hub hosts Ge-DIX and the landings of BlueMed and Blue. Rai Way opened an edge data centre at Granarolo in December 2024, and Leonardo runs its davinci-1 supercomputer in the city. Quadrivium Digital is fitting out a cable-ready data centre in Sturla, on the eastern seafront. KevlinX, backed by Macquarie, plans a campus on a former oil depot at Fegino in the Polcevera valley.
Advantages
-
Subsea routes. Genoa gives cables from Africa, the Middle East and India a landing point close to Milan.
-
Room for cables. Sparkle's landing platform has space for six more systems, and Quadrivium's site can take eight.
Challenges
-
Zoning. Genoa's city plan makes no provision for data centres. The Fegino project needs a zoning variance, an environmental assessment and soil remediation, and in November 2026 the city said it was still in pre-review.
-
Neighbours. Sturla residents have raised concerns about the energy use and noise of the new site there.
Power and Policy
Terna runs the transmission grid, and e-distribuzione distributes power in Genoa. New campuses need a change to the city plan as well as the national single authorisation for data centres created in 2026.