Wallingford council discloses details of data center host fee agreement

MadalineDunn

MadalineDunn

June 28, 2021

Following a series of delays, Wallingford council has revealed its revised host agreement with Gotspace Data Partners, the tech company that seeks to build a number of facilities on two properties in the town. The revised agreement comes as the council voted five to 4 for its approval.

Gotspace will potentially build two data center campuses; one is 205 acres, while the other is 138 acres. As part of the agreement, the facilities, when built, must measure 45 ft tall or under, and street-facing buildings will also be required to comply with town regulations on color, fencing and light fixtures.

As stipulated in the agreement, host fees for each building with a capacity of 32 MW, or above, would be $1.5 million a year. Buildings with a capacity of 16MW or below would see a $500,000 annual host fee. According to The Record-Journal, “conceptual plans” reveal that 10 data center buildings would potentially fit on the properties.

Get Started

Ready to Level Up Your Data Center Strategy?

Tell us what you're looking for. We respond within one business day.