Published in Northern Virginia

Data center approval sought by Finmarc for Telos HQ campus

Feb 17, 2023 | Posted by MadalineDunn

Finmarc Management Inc. has reportedly applied six years in advance for a data center development. Some have suggested that this is to avoid being halted by future restrictions imposed by legislation; others have argued it's due to energy capacity limitations in the Ashburn area.

Although Loudoun County's Board of Supervisors voted back in September, to prevent new data center development in the area along Route 7, the land parcel's zoning in the area hasn't yet caught up. This means that landowners can push ahead with data center development approval as the regulatory framework doesn't yet apply fully. The parcel located at 19886 Ashburn Road, owned by a number of LLCs all "care of" Bethesda-based Finmarc, is one of these locations, and reports are that Finmarc recently applied to the county for a site plan to build a 180,000-square-foot data center there.

While this has not been well-received by some on the Board, they have admitted that they don't have the legal recourse to stop it from happening. One Supervisor, Mike Turner, D-Ashburn, said he was looking for ways to incentivize data center developers to not target the area. 

There are 575 data centers in Northern Virginia.

Proposed site for Amazon's Ashton Ave Project in Virginia
Posted in Amazon: Ashton Ave Source: Prince William County
Conceptual plan for Headwaters Site Development's project in Virginia
Posted in Headwaters: Catlett, VA Source: Fauquier Times
SDC Capital Partners acquired 97-acres of data center-zoned land in Virginia
Posted in SDC Capital: Twin Creeks Source: Google Maps
Proposed sitemap for Tract's Mountain Road Technology Park
Posted in Tract: Mountain Road Tech Park Source: Tract
Conceptual plan for Peterson Companies' Project Sisson in Stafford County, Virginia
Posted in Peterson: Project Sisson Source: Peterson Companies
Area for Desper Creek Technology Campus in Louisa County
Posted in Desper Creek Technology Campus Source: US Army Corps of Engineers
Sitemap of Oasis Digital's Dahlgren West Campus
Posted in Oasis Digital: Dahlgren West Campus Source: Dahlgren West
NTT's VA6 Data Center under construciton
Posted in NTT: VA6 Source: NTT
Rendering of Menlo Digital's MD-DC2 Data Center in Sterling
Posted in Menlo: MD-DC2 (Sterling) Source: Menlo Digital
Rendering of Menlo Digital's MD-DC1 Data Center in Herndon
Posted in Menlo: MD-DC1 (Herndon) Source: Menlo Digital
Existing buildings at Starwood's Alexandria site
Posted in Starwood: Alexandria, VA Source: Google Maps
Rendering of H5's Herndon Data Center in Virginia
Posted in H5: Herndon Source: H5 Data Centers
The site for Stack Infrastructure's Proposed Development in Fredericksburg, Virginia
Posted in Stack: Fredericksburg, VA Source: Fredericksburg City Council
Proposed site for The Hiddenwood Assemblage Campus in Aldie, Virginia
Posted in Hiddenwood Assemblage Campus Source: Google Maps
Stack Infrastructure's Sitemap for Loudoun County Campus
Posted in Stack: Loudoun County Campus Source: STACK Infrastructure
Proposed Site For Iron Mountain's Manassas Campus Expansion
Posted in Iron Mountain: VA-8 |
The two parcels targeted for development by Springfield East & Kettler
Posted in Springfield East: Leesburg, VA Source: Leesburg Town Council
BlackChamber's Proposed Tuscarora Crossing Site in Leesburg, VA
Posted in Tuscarora Crossing Campus |
Area map of John Marshall Commons Tech_Park in Virginia
Posted in John Marshall Commons Tech Park Source: Prince William County Planning Commission
Area map for Devlin Tech Park in Bristow, Virginia
Posted in Amazon: Devlin Tech Park |
DataBank Culpeper Campus Revised Sitemap
Posted in DataBank: IAD5 Source: DataBank
Rendering of Iron Mountain's VA6 Data Center
Posted in Iron Mountain: VA-6 Source: Iron Mountain
Rendering of Spring Valley Tech Park in Leesburg
Posted in Active Infra: Spring Valley Tech Park Source: Active Infrastructure
Site Plan of Vantage VA3 Campus in Ashburn
Posted in Vantage VA3 Campus Source: Vantage Data Centers
Layout of Amazon's planned data centers in Herndon
Posted in Amazon: IAD-500 Source: Fairfax County
Site of SDC Capital's Belmont Innovation Campus in Virginia
Posted in Belmont Innovation Campus Source: Loudoun County
Location Total SqFt Gross SqFt Power (MW)
CyrusOne Northern Virginia Sterling V 383,000 SqFt
NN Request Dataset
NTT Gainesville VA Campus 518,080 SqFt
295,680 SqFt
NN Request Dataset
CorScale: Gainesville 2 60,000 SqFt
288,000 SqFt
NN Request Dataset
1780 Business Center Drive (VA3) Digital Realty 264,888 SqFt
NN Request Dataset
CloudHQ MCC2 392,565 SqFt
250,144 SqFt
NN Request Dataset

Ready to Level up Your
Data Center Strategy?