CoreSite has announced it has completed the first phase of its second data center in Chicago.

CoreSite has designed and built a 169,000 square foot facility with a total of 18 megawatts of capacity, known as “CH2,” in the heart of downtown Chicago. The CH2 data center is one of the first purpose-built, ground-up development in downtown Chicago, and CoreSite has completed Phase 1, representing 56,000 square feet and six megawatts of capacity.