Published in Microsoft East Wenatchee

Microsoft buys land for data center campus in Central Washington

Mar 29, 2021 | Posted by Eric Bell

Microsoft has purchased 170 acres of underdeveloped land north of Pangborn Memorial Airport for $19.3 million. The investment could well rise to over $1 billion in the next five years to build a multi-phase data center. 

Microsoft has also started leveling the construction site in preparation for developing one of the three proposed structures. According to the building permit, the building will be over 244,000 square feet, and the company values it at $409 million.

Microsoft has agreed to pay for a substation, transmission line and other improvements to support its large power needs. The substation is expected to cost $24.9 million and should be completed by May 2022.

Microsoft East Wenatchee is located at 925 Urban Industrial Way, East Wenatchee, WA 98802.

State of Azure Locations as of July 2019
Posted in Microsoft Azure Source: Microsoft
Conceptual Azure Regions and Availability Zones diagram
Posted in Microsoft Azure Source: Microsoft

Microsoft Azure has 349 sites in 14 regions.

State of Azure Locations as of July 2019
Posted in Microsoft Azure Source: Microsoft
Conceptual Azure Regions and Availability Zones diagram
Posted in Microsoft Azure Source: Microsoft

Ready to Level up Your
Data Center Strategy?