Vantage Santa Clara SC2

Login to Add Favorite Login to
Site: Vantage Santa Clara SC2

Company: Vantage Data Centers
Metro: San Francisco Bay Area
State: California
Country: United States
Region: North America
Region: Americas
Short Code: V5, V6
Address: 725 Mathew St, Santa Clara, CA 95050
Site Stats:
Current Under Construction Potential Expansion Total at Full Buildout
Building SqFt: 541,000 541,000
Gross SqFt:
Usable SqFt:
Office SqFt:
Power (MW): 21.00 48.00 69.00

Vantage's second campus in Santa Clara which will contain V5 and V6. The Vantage's long-term plan calls for four data center buildings totaling 541,000 square feet and 69 megawatts of critical load.

Site Address Gross SqFt Usable SqFt Power MW
V5 To be built 2H 2017
V6 To be built 2H 2017
Total 21
  • 9-acre campus (less than 2 miles from SCI)
  • Three (3) four-story data centers planned
  • 541,000+ sq. ft. of data center space
  • 69MW of critical IT load
  • Phase I will bring 21MW of new capacity in Q3’19

Map and Nearby Locations:

725 Mathew St, Santa Clara, CA 95050

SITES within 15 miles of Vantage Santa Clara SC2

Show SqM



Distance Site name SqFt MW
0.87 miles 1100 Space Park (SCL1) Digital Realty 167,951 9.00
0.87 miles telx SCL1 2,846 0.15
0.89 miles 1525 Comstock - Digital Realty 29,234 4.50
0.89 miles Internap Santa Clara SJE014 7,500 2.00
0.93 miles Colovore 24,000 9.00
0.94 miles 1500 Space Park - Digital Realty 51,615 9.00
0.94 miles Level3 San Francisco (Santa Clara)
0.96 miles 1725 Comstock - Digital Realty 21,000 3.38
0.97 miles Integra San Francisco 6,144 1.75
1.04 miles Layer42 Santa Clara
The data center is expected to be completed in Spring of 2019.
The data center is expected to be completed in Spring of 2019.
Rendering of Vantage's New Campus in Santa Clara

The data center is expected to be completed in Spring of 2019.

Empty Lot in a Satellite Picture Taken Before Start of Construction
Source: Google Maps

November 2019

Santa Clara II Campus Data Sheet (PDF)