CyrusOne Chandler Phoenix Campus

2335 South Ellis Street

Operated by:

Located on a 85-acre campus in Chandler, the company plans to build a nearly 2 million square-feet data center campus.

Building

  • SOC 1 type 2, SOC 2 type 2, PCI DSS (section 9 and 12), HIPAA, ISO 27001, FISMA, built to TIA 942 Class 4 specifications
  • High-performance computing (HPC) capable; supports 250 watts per square foot, with the ability to support over 1,000 watts per square foot
  • Historically free of seismic activity, tornados and hurricanes
  • Carrier-neutral and part of the CyrusOne National Internet Exchange (IX)
  • 100% uptime service-level agreements on power
  • 24/7 year-round staffed network operations center and remote hands support
  • Dedicated cages and private suite options available

Power

  • Multiple levels of redundancy available within the same footprint (N, 2N)
  • 160 MW on-site substation
  • Dual underground power feeds to on-site substation
  • Dual-input power-distribution units (PDUs) with static transfer switches.
  • Scalable to six 2.25MW Detroit Diesel dedicated generators pre-wired for additional capacity.
  • 5,000-gallon diesel fuel belly tanks

Map and Nearby Locations:

2335 South Ellis Street
Click Map to begin Search

Sites within 15 miles of CyrusOne Chandler Phoenix Campus

Show SqM
Distance Site About
0.02 miles CyrusOne PHX1
0.07 miles CyrusOne PHX5
0.09 miles CyrusOne PHX3
0.09 miles CyrusOne PHX2
0.14 miles CyrusOne PHX4
0.17 miles CyrusOne PHX10
0.20 miles CyrusOne PHX9
0.22 miles CyrusOne PHX6
0.30 miles CyrusOne PHX7
0.31 miles CyrusOne PHX8
0.32 miles Aligned: PHX-06
PHX06 is a two-phase development that will total 456,946 SqFt
0.43 miles redIT Chandler
0.43 miles 2121 S Price - Digital Realty
In 2010, DRT acquired this site from 365 Main portfolio.
0.47 miles Aligned: PHX-04
Construction began in July 2022.
0.49 miles H5 Phoenix
H5 acquired the site when it bought NextFort in January 2016H5 acquired the site when it bought NextFort in January 20
0.64 miles 1900 S Price - Digital Realty
The Building is 1 story Flood Zone: Zone X Seismic Zone: Zone 1
2.07 miles 2500 W Frye
2.07 miles Internap Phoenix 2500 W Frye Rd
The site was launched in 2018 in conjunction with Lincoln Rackhouse, Internap's landlord
4.96 miles 2010 East Centennial
Digital Realty sold the office & data center building in 2018 to an unnamed company. We believe Fox Sports is the tenant.
5.27 miles 2055 E Technology - Digital Realty
Located in the Arizona State University Research Park and downtown Phoenix Central Business District, the facility was redeveloped in 2007. Digital Realty's 76,000 square foot data center at 2055 E. Technology Circle is approximately 15 miles away from downtown Phoenix. The building is SOC2 certified with 24/7 security and critical facilities management.
6.66 miles OneNeck Phoenix 1
9.71 miles OneNeck Phoenix 2
9.98 miles EdgeConneX Phoenix
10.48 miles Evoque PHX1
12.43 miles Cyxtera Phoenix PH1
12.43 miles PhoenixNAP-Phoenix
12.52 miles XO: 3930 Watkins
13.79 miles DataBank PHX2
13.81 miles redIT Phoenix
13.81 miles Internap Phoenix
13.81 miles Iron Mountain Phoenix
Iron Mountain acquired the site in January 2018 in a $1.34 Billion acquisition of IO Datacenter's operations in the United States which included 4 sites (Phoenix, Scottsdale, Edison New Jersey, and Columbus Ohio) 41-acre Iron Mountain Hyperscale-Ready campus 588,000 gross square feet 32 MW – redundant feeds
14.45 miles STACK Phoenix PHX02 Campus
STACK Infrastructure plans to develop a five-building, 246MW campus in the heart of central Phoenix, Arizona. The more than 1.7 million square foot campus will run on 100% renewable energy.
14.52 miles Stack: PHX02 Building 2
STACK Infrastructure plans to develop a five-building, 246MW campus in the heart of central Phoenix, Arizona. The more than 1.7 million square foot campus will run on 100% renewable energy.
14.54 miles Stack: PHX02 Building 3
STACK Infrastructure plans to develop a five-building, 246MW campus in the heart of central Phoenix, Arizona. The more than 1.7 million square foot campus will run on 100% renewable energy.
14.61 miles Stack: PHX02 Building 4
STACK Infrastructure plans to develop a five-building, 246MW campus in the heart of central Phoenix, Arizona. The more than 1.7 million square foot campus will run on 100% renewable energy.
14.67 miles Stack: PHX02 Building 5
STACK Infrastructure plans to develop a five-building, 246MW campus in the heart of central Phoenix, Arizona. The more than 1.7 million square foot campus will run on 100% renewable energy.
14.74 miles QTS Phoenix
QTS expansion with an 84-acre campus with 5 planned buildings with 280 MW of critical power
15.06 miles Windstream Phoenix
15.06 miles CenturyLink: 811 S. 16th
15.10 miles Lumen Phoenix 1
15.23 miles GoDaddy: Gilbert, AZ
15.43 miles Comarch Mesa
15.71 miles CyrusOne Mesa
15.73 miles Amazon: Pecos Campus, Mesa
Amazon.com Inc. looks to be getting closer to starting construction on two separate data center projects in southeast Mesa.
15.99 miles EdgeCore Mesa
The 1.25 million sqft campus can include up to 7 buildings. The first of the seven data halls is complete and totals 178,252 sqft with an adjoining 20,000 sqft office and support space.
16.50 miles NTT PH3
16.51 miles NTT Phoenix Campus
The 102-acre campus will have seven data centers offering a total of 240 MWs of critical IT load and 1.5 million sqft of space, along with an on-site dedicated substation. The first data center will offer 36MW across six 6MW vaults and 126,000 sqft
16.56 miles Amazon: Elliot Campus, Mesa
Amazon.com Inc. looks to be getting closer to starting construction on two separate data center projects in southeast Mesa. The Elliot campus is a 42.9-acre property located off Elliot Road, adjacent to Apple's existing data center in Mesa.
16.60 miles NTT PH1
16.63 miles AIS Van Buren (VBDC)
16.63 miles XO: 120 Van Buren
16.63 miles 120 E Van Buren - Digital Realty
120 E Van Buren is Phoenix's carrier hotel and the building is the best connected in Phoenix. The building is also home to many colocation operators including AIS, QTS, Sungard, XO
16.64 miles QTS Phoenix Van Buren
QTS acquired this site via the Carpathia acquisition in 2015.
16.70 miles NTT PH2
16.88 miles Apple Mesa
The site was a former a sapphire-glass factory that supplied glass to Apple. The glass maker filed for bankruptcy and vacated the building in 2014. Now the 1.3 million square foot building is one of Apple’s data centers
17.97 miles Lumen Phoenix 2
18.46 miles DataBank Phoenix PHX1
18.82 miles Liquid Web Phoenix
18.83 miles eBay Arizona
eBay's data center is also known as Project Mercury.

CyrusOne Chandler Phoenix Campus Data Center Photos


Construction Almost Complete in 2013
Source: Bergelectric

First Chandler Facility Under Construction in 2012
Source: Bergelectric

Data Hall
Source: CyrusOne
Energy Labs Hybrid Systems utilize a perimeter base frame constructed of Structural Steel to insure minimum deflection
Energy Labs HVAC Cooling System

Energy Labs Hybrid Systems utilize a perimeter base frame constructed of Structural Steel to insure minimum deflection

Source: CyrusOne

The Architectural Beautiful Entrance to CyrusOne's Chandler Facility
Source: JE Dunn

Elegant Lobby
Source: JE Dunn

Drop Ceiling
Source: JE Dunn

Tech Break Room
Spartan decor, but functional
Lobby for Building #4

Spartan decor, but functional


Building #4 Rooftop Mechanical

Operating Company

CyrusOne Inc, incorporated on July 31, 2012, is an owner, operator and developer of enterprise-class, carrier-neutral, multi-tenant datacenter properties. CyrusOne's data centers are purpose-built facilities.

The CyrusOne National IX Platform (the National IX Platform) delivers interconnection across states and between metro-enabled sites within the CyrusOne footprint and beyond. The platform enables data transfer and accessibility for customers by uniting all of the Company’s data centers. CyrusOne’s portfolio is located in several domestic and international markets. It has domestic properties in Chicago, Dallas, Houston, Phoenix, San Antonio and Cincinnati.

Company History:


July 2010: Cincinnati Bell acquires CyrusOne [r3]
Jan 2013: CyrusOne IPO [r2]
July 2014: Acquired Cervalis [r1]

References:


r1. Businesswire link July 1, 2015
r2. NASDAQ.com link Jan 18, 2013
r3. CyrusOne PR link

70 Facilities Owned
27 Markets Served
933.42 Megawatts
View Company

News

Read More News

Files

Name Date Added Description
cyrusone_ss_phx_datacenters_2017a_21mar17 May 2017

Data Sheet

2022-phx1-phx8_phoenix-chandler September 2023

PHX1-PHX8 Chandler campus overview